Screen a solar farm site

Compare modeled solar yield, usable land constraints, and grid evidence before shortlisting a U.S. solar farm site.

Start with a parcel boundary and the proposed AC export at the point of interconnection. Use Fetch to compare modeled solar resource and nearby grid infrastructure. Use Enrich to measure parcel-wide constraints. Then check the grid operator’s current queue and the project’s study or agreement before treating a connection as feasible.

Compare solar yield and grid context at the same point

Use a verified point in each candidate area and keep the same reference system across the comparison. If you start with a large search area, find the parcels intersecting the project polygon first. Set INVARIANT_API_KEY to your API key.

This example uses the Ohio location published in PJM’s Nottingham Solar interconnection agreement for AE2-290. PJM interconnection agreement, schedule of generating facilities.

curl --fail-with-body --max-time 75 -sS 'https://api.invariant-ai.com/v1/fetch' \
  -H "X-API-Key: $INVARIANT_API_KEY" \
  -H 'Content-Type: application/json' \
  --data '{
    "lat": 40.189455,
    "lng": -81.041113,
    "fields": [
      "ghi_annual_kwh_m2_day",
      "pv_specific_yield_kwh_per_kw",
      "pv_capacity_factor_pct",
      "nearest_substation_distance_m",
      "nearest_substation_max_voltage_kv",
      "interconnection_queue_active_capacity_county_mw"
    ]
  }'
Fields How to use them
ghi_annual_kwh_m2_day Daily solar resource on a horizontal surface, averaged over the year. Compare the same model vintage across sites.
pv_specific_yield_kwh_per_kw and pv_capacity_factor_pct Annual AC energy per kW of DC nameplate and modeled capacity factor for a reference fixed-tilt system. Use the same assumptions to rank initial candidates. Run project-specific scenarios for tracking, inverter sizing, shading and losses.
nearest_substation_distance_m and nearest_substation_max_voltage_kv Straight-line distance and mapped voltage at the nearest station in range. Use them to locate connection candidates and investigate a feasible line route.
interconnection_queue_active_capacity_county_mw County total for active generation and storage requests in a dated Berkeley Lab snapshot. Check the grid operator’s current records for status and proposed connection point.

In a direct public source check on November 24, 2026, the Solar Resource API returned 3.85 kWh/m²/day of annual-average daily horizontal irradiation at the Nottingham reference point. PVWatts v8 returned 1,225.18 kWh of annual AC energy for 1 kW DC, a 13.99% capacity factor on the DC nameplate basis. The request used standard modules, fixed open rack, tilt equal to latitude, azimuth 180°, 14% losses and a 1.2 DC-to-AC ratio. The response identified an NSRDB 2020 typical-year weather file. These figures describe the reference case at the coordinate. Replay the public Solar Resource request · Replay the public PVWatts request.

Check how much land the layout can use

Query the parcel containing the point. Repeat for each tract under consideration and verify the returned boundary against the project’s legal description.

curl --fail-with-body --max-time 75 -sS 'https://api.invariant-ai.com/v1/enrich' \
  -H "X-API-Key: $INVARIANT_API_KEY" \
  -H 'Content-Type: application/json' \
  --data '{
    "lat": 40.189455,
    "lng": -81.041113,
    "fields": [
      "parcelnumb", "gisacre", "zoning",
      "parcel_slope_pct_mean", "parcel_slope_valid_frac",
      "wetland_fraction_of_parcel", "parcel_flood_sfha_fraction"
    ]
  }'

Treat county acreage as a starting area. Check where the grade, mapped wetland and flood polygons, setbacks and access routes intersect the layout. Overlay the constraints before subtracting area so overlapping polygons count once. Check each connected buildable block and leave room for access, drainage and electrical equipment. Review mean slope alongside its valid-area fraction and inspect the grade in the intended array area. Confirm allowed use with the local zoning authority and field-verify wetland limits as needed.

Read status in Fetch and parcel_match and field_omissions in Enrich. Record missing coverage as unresolved and keep the method, units and source vintage. Enrichment field catalog · Responses and provenance.

Verify the proposed connection in the project record

At Nottingham 138 kV, PJM studied a separate request, AG2-082, for Energy Pastures Solar. Both study phases list 200 MW maximum facility output and 133.4 MW studied capacity. The published allocation changed from $2,326,000 in Phase I to $4,164,556 in Phase II. The estimates apply to that request and study version. Compare the latest study, connection agreement, cost scope and target dates for the project you are screening. PJM Phase I study · PJM Phase II study.

Keep DC module nameplate, AC export request, studied capacity and contracted rights in separate columns. Record the proposed station and voltage, route, latest queue status, applicable upgrade costs and the date each source was checked.